(Courtesy of TGSF)
Turf installation is almost complete on the new Fair Hill track. The pump house for irrigation is being installed. Fence post installation around all three arenas is complete and the footing installation has commenced. Fence posts are also being installed for the rail of the race track as well as for crowd barriers. Trees and shrubs will be going in shortly.
The entire project is scheduled to be wrapped up by the end of 2019 and will include three arenas in the infield; a new irrigated turf track with safety upgrades – wider, more sweeping turns and all new turf; and a new CCI5* cross country course.